November 2016 – UrbanSurrey

The official lighting of Surrey’s Christmas Tree was held back on November 19th as part of the city’s 6th annual Tree Lighting Festival. Since then, the 55 foot tree along with other festive lighting has lit up the plaza, in what is one of the best Christmas Tree displays to be found anywhere, and arguably the best in the Metro Vancouver area. The tree itself is billed as BC’s tallest Christmas Tree, and is a must see for anyone that hasn’t yet in person.

Over the past weekend a 2nd tower crane was added at the SFU Surrey expansion project, bringing the total number of cranes in the immediate vicinity to 5, and the total number in City Centre to 8. While the building under construction will only be 5 storeys in height, its large footprint and accelerated construction schedule are both likely reasonings for the addition of a 2nd crane. It is also worth noting that the building will be higher than a typical 5 storey building, with a planned height of 35m (115′) according to a Surrey Planning Report. For comparison, this is closer in height to a 9 or 10 storey condominium building.

This newest crane adds to the growing number of cranes in Surrey’s rapidly changing skyline. The number of cranes currently up is unprecedented in the city’s history, and a visible sign that development within City Centre is now accelerating. Given the large number of development applications already underway for future towers, the sight of cranes across Surrey’s skyline will likely only continue to grow in the coming years.

Further to news earlier this month on the moving forward of the Veterans Village Project, on the site of the Whalley Legion, more details were released late last week showing a major re-design of the project.

The previous concept prepared by Michael Green Architecture for a twin-tower development has since been replaced by a single, ‘stepped’ tower concept over what appears to be a 2-storey podium. In addition, a large portion of the site is shown to be dedicated as an open plaza/park space, forming what would be Surrey’s equivalent to Victory Square in Downtown Vancouver. The proposed plaza would provide a new space for Remembrance Day ceremonies in Surrey and serve as a permanent memorial space.

Despite the reduced scope of the project from a twin tower concept to a single tower, the project continues to take design inspiration from the twin tower Canadian National Vimy Memorial in France. As depicted in the concept, the tower features 2 red decorative beams running up the height of the tower, reminiscent of the memorial. Still no confirmation on height, however a Surrey Now article mentions a height of between 16-28 storeys.

While no application has yet been submitted on the project, the developer Lark Group, hopes to begin site preparation and construction by as early as Spring 2017. The project is said to still be seeking funding sources, some of which could come through Federal Infrastructure funding, currently being lobbied for.

http://www.thenownewspaper.com/news/400750081.html

http://journalofcommerce.com/Projects/News/2016/11/BC-Veterans-Village-project-a-step-closer-to-reality-1019666W/

The much anticipated government funding for the SFU Surrey expansion was finally announced today at a much-publicized event on the Surrey campus. At the event, Prime Minister Justin Trudeau and Premier Christy Clark announced Federal and Provincial funding in the amount of $45 million each to the project. This funding will go towards the already underway first phase of a 3-phase expansion of the campus, with an additional $26 million from SFU and donors to fund future phases 2 and 3 on the remaining recreation centre surface parking lots.

While today’s announcement was news to many, UrbanSurrey first reported on the SFU expansion back in early June 2016 after a development application was submitted by SFU on the subject site at University Drive and 102 Avenue. Since then, today’s announcement has revealed that the new building is on track to open in Spring 2018, and that it will house the proposed Energy Systems and Environmental Engineering Program – an interdisciplinary engineering stream that will support the clean tech and sustainable energy sector.

New renderings were also released today, similar to those posted by UrbanSurrey back in July. The Bing Thom designed building will be a great addition to the City Centre as part of a rapidly changing University Drive.

https://www.sfu.ca/sfunews/stories/2016/sfu-moves-ahead-with-surrey-campus-expansion.html

The fast moving SFU Surrey expansion project, which began excavation just 2 months ago, has now installed its crane. The 5-storey, Bing Thom Architects designed Sustainable Energy and Environmental Engineering Building project is proceeding at a rampant pace to meet an April 2018 deadline for substantial completion. As of now, the north end of the site adjacent to the under construction Prime development is nearly completely dug, with just the south end remaining to be dug before construction can commence on the underground levels of the building.

Today’s installation adds to the growing number of cranes in Surrey City Centre, which now has a total of 7 cranes, with 1 more likely on the way within the next month. The presence of this many cranes represents the largest construction boom ever experienced in the City Centre, and a sign that momentum is picking up for development in the area. The next 5-10 years are likely to bring more transformation to the area than its seen in its entire history.

Initially announced back in the Fall 0f 2015, the Whalley Legion Veterans Village project took a major step forward today, announcing a partnership with Surrey-based developer Lark Group, to develop twin towers on the site of the existing Whalley Legion at 13525 106 Ave.

As per the news release, the twin tower project of unspecified height will be a multi-purpose facility and a centre of excellence in clinical and rehabilitation services for Veterans and first responders. It will offer a mixture of social and affordable housing, assisted living, a therapeutic centre, community gardens, research centre, and space for the delivery of health care programs and services.

The news release states that the next step in the process is to work with Lark Group to finalize the scope of the project, and it is expected that site preparations and construction could be underway by spring 2017. This timeline seems ambitious given there has yet to be a development application submitted for the project, and given the time necessary to move the application through the approvals process. With Lark Group as the partnering developer however, the project is now very likely to move forward, given Lark Group’s experience in developing large projects in Surrey, most notably the City Centre 1 and City Centre 2 office towers adjacent to Surrey Memorial Hospital.

Aside from being a major redevelopment of the Whalley Legion itself, the iconic twin tower concept for the project designed by Michael Green Architecture could be a catalyst for rejuvenation of the area between 104th Avenue and 108th Avenue. The project is located directly adjacent to Surrey’s notorious 135A “Strip”. So far not many details have been released on the towers themselves, only that the design is conceptual, and that it will be greater than 20 storeys in height. When complete, the facility will be the first of its kind in Canada.

http://www.larkgroup.com/legion-veterans-village-project-takes-a-major-step-forward/

More on the project:

http://www.legionbcyukon.ca/content/canadas-first-veterans-village

Growth in Surrey City Centre accellerating – UrbanSurrey

On Friday, an article was published in the Globe & Mail by urban politics and issues writer Frances Bula titled ‘Surrey’s vision for the future is slow in coming‘, shining a spotlight on the city centre’s transformation, that has indeed been slow in coming. Up until now.

A Brief History of Surrey City Centre – 1991-2005

The vision for Surrey’s City Centre is nothing new. The first City Centre Plan was completed back in 1991, and was only just recently updated as of January this year after a lengthy 10-year review beginning in 2006. Looking back at how the city centre has developed since that initial plan’s adoption, it’s clear to see that development through much of the 1990s and 2000’s had been sparse and slow to materialize, sparking the need for a renewed vision to move the city centre forward. Aside from an initial spike in development between 1994-1995, when SkyTrain was first extended to the area, and a total of 7 high-rise towers were completed within a short time span, the decade that followed was markedly different.

Intrawest/Intracorp initially had a master plan for a community around Gateway Station in the early 1990’s which was to include a total of 5 high-rise office towers, and 11 high-rise residential towers. 3 of these residential towers and 1 of the office towers were completed in the 1994-1995 boom, including the 18-Storey signature Station Tower. Following this initial spike, the remaining lands sat vacant for over a decade, until 3 of the initially slated high-rise residential sites were eventually developed as 4-storey condo buildings between 2008-2011. Intrawest/Intracorp has since sold of the remainder of their lands to other developers, with the initial master plan never coming to fruition.

Another 90’s master planned community which was to see a number of towers developed around King George Station saw only 1 tower built in 1994, with the remaining lands sitting vacant for over a decade as well, until eventually being bought and developed in the mid-2000’s – first as Infinity, then later evolving into Concord Pacific’s Park Place.

Completion 1991-1995:

  • 1994: Cornerstone 1 & 2 (Gateway) | 18 & 21-storey condo towers
  • 1994: Station Tower | 18-storey office tower
  • 1994: Odyssey Tower | 21-storey condo tower
  • 1994: Balmoral Tower | 15-storey condo tower
  • 1995: Grandview Court | 16-storey condo tower
  • 1995: Observatory (Gateway) | 22-storey condo tower

In the decade between 1996 and 2005, development in Surrey City Centre was indeed so slow that only 1 tower was built – the city’s iconic, Bing Thom designed, Central City office tower, completed in 2003 as part of a massive redevelopment of former Surrey Place Mall by ICBC into a re-branded shopping centre, TechBC (later SFU) university, and office tower.

Completion 1996-2005:

  • 2003: Central City – 26-storey office tower, university, retail

Surrey City Centre’s Turning Point – 2006-2015

Following a decade of very little development activity which saw only 1 tower built between 1996 and 2005, a total of 4 new high-rise towers were built in Surrey City Centre between 2006 – 2010.

Completion 2006-2010:

  • 2006: Infinity (now Concord Park Place) | 36-storey condo tower
  • 2009: D’Corize | 22-storey condo tower
  • 2009: City Point | 21 and 25-storey condo towers with retail

In the 5 years that followed, development activity grew more. A total of 6 high/mid-rise towers were completed between 2011-2015, along side the new Surrey City Hall, the Bing Thom designed City Centre Library, and Surrey’s new civic plaza which will see future expansion.

Completion 2011-2015:

  • 2011: Park Place | 2 x 36-storey condo towers
  • 2011: Surrey City Centre Library
  • 2013: Ultra | 35-storey condo tower
  • 2013: Surrey City Hall
  • 2014: City Centre 1 | 12-storey office tower
  • 2014: Coast Capital headquarters | 9-storey office tower
  • 2015: Wave | 28-storey condo tower

In total, the 10-year period between 2006 to 2015 saw more development activity in Surrey City Centre than the previous 15 years combined, along with a new civic heart. Following a period of very little growth between 1996 and 2005, a sure sign that the tide may be changing.

2016 and onward

Since the relocation of Surrey City Hall to the city centre in 2013, and the opening of Civic Plaza, investment in the area has markedly picked up, with a long list of active development applications now in process at the city. Following a relatively strong decade of growth between 2006 and 2015, in 2016, Surrey City Centre was showing signs of coming to fruition, and ripe for the adoption of the new Surrey City Centre Plan. In the past year, 2 towers have been completed, with 4 more scheduled for completion in 2017, and an additional 4 scheduled for completion in 2018. In 2017, this will include the iconic new 52-storey 3 Civic Plaza, Mixed-Use (Hotel, Office, Condo, University, Retail), which is already re-defining and transforming the city centre’s core and image. In total the 2016-2020 period will see a total of 12 significant buildings completed, up from 8 in the previous 5 years.

Completion 2016-2020:

  • 2016: University District (Phase 1) | Condo, Office, Retail | 32 Floors
  • 2016: Park Avenue East | Condo | 36 Floors
  • 2017: Park Avenue West | Condo | 39 Floors
  • 2017: 3 Civic Plaza | Condo, Hotel, University, Retail |52 Floors
  • 2017: Bosa’s Gateway Place |Office, Retail | 5 Floors
  • 2018: Prime on the Plaza | Condo, Retail | 37 Floors
  • 2018: Evolve | Condo, Office, Retail | 36 Floors
  • 2018: City Centre 2 | Office, Retail | 12 Floors
  • 2018: SFU Sustainable Energy / Engineering Building | 5 Floors
  • 2019 (estimated): Innovation village | Care Facility, Office, Seniors | 12 Floors
  • 2020 (estimated): Concord Park Boulevard | Condo | 42 Floors
  • 2020 (estimated): West Village Phase 5 | Rental, Office, Retail | 44 Floors

Looking ahead to 2021 and beyond, it is clear to see that the pace of growth in Surrey City Centre is only set to intensify if the number of approved and active development applications are any indication. In total, aside from buildings now under construction and scheduled for completion by 2020, beyond this there are 47 additional towers under active application or known to be in the planning stages in Surrey City Centre. While the timeline for completion of many of these towers is uncertain based on market conditions, it is likely that many will see completion within the next decade, given Surrey’s strong population growth, doubling Vancouver in growth between 2011-2016. While much of this growth has been concentrated in newer developing areas of the city such as South Surrey, South Newton, and Cloverdale, it is reasonable to assume that Surrey City Centre will start to take on a greater share of future growth as it reaches a critical threshold of density (which it appears to be now), and its subsequent image and desiraiblity improves. Combine this with the affordability crisis north of the fraser, and the comparable price of condos, Surrey City Centre begins to become more and more attractive.

With this direction that Surrey City Centre is heading, already a number of major developers in the region have significant land holdings in the area, including projects completed, under application, or in the planning stages.

Completion beyond 2021 (Proposed and under application):

  • GEC Education Mega Centre | Student Housing, Hotel, Institutional | 50 Floors
  • University District (Phase 2) | Condo, Office, Retail | 26 + 32 Floors
  • Hub at King George | Condo, Office, Retail | 12 + 20 + 32 + 38 + 39 + 42 Floors
  • Wynd |Condo | 28 Floors
  • City Centre 3 | Office | 8 Floors
  • 13778 100 Ave | Condo | 20 + 46 Floors
  • Tien Sher 108 Ave & King George |Condo, Retail | 6 + 35 + 37 + 46 Floors
  • Old Yale & 133 St | Condo | 22 Floors
  • Seagate Gateway | Condo | 30 + 37 Floors
  • Holland Point | Condo, Office Retail | 30 + 36 + 41 Floors  
  • 98th & King George | Condo, Hotel | 30 Floors
  • 9677 King George | Care Facility, Office | 18 Floors
  • Anthem Properties | Condo, Office, Retail | 7 Towers
  • 133 St & 103A Ave | Condo | 18 Floors
  • West Village Phase 6-8 | Condo, Office, Retail | 37 + 38 + 42 Floors
  • City Centre YMCA
  • Bosa University District (Future Phases) | Condo, Retail | 5 Towers
  • Bosa Gateway Place (Phase 2-3) | Condo | 2 Towers
  • Veterans Village / Whalley Legion | Care Facility, Office | 20 Floors
  • SFU Expansion (Phases 2-3)

This list will of course continue to grow as new applications are submitted.

For an active list and map of Surrey City Centre projects, see the UrbanSurrey Active Projects Page

Updated May 10, 2017

March 2019 – UrbanSurrey

A development application has been submitted for a mixed-use tower at 10731 King George Blvd just south of 108 Avenue. The subject site is made up of 3 existing lots which currently contain a run-down 2-storey commercial/residential building, and a 1-storey medical clinic.

The subject application is proposing to consolidate the 3 lots into 1, rezone the site from CHI to CD (based on RM-135 and C-15), as well amend the City Centre Plan to permit a 345-unit mixed-use development. The site is currently designated ‘Mixed-Use (3.5 FAR)’ under the City Centre Plan. In addition to redevelopment of the site, the application would also dedicate a portion of future 107A Avenue just to the South. The 2 adjacent properties to the South are currently owned by the City for the purposes of completing this new road connection.

View of Site from King George Blvd Subject Site within City Centre Plan – Designated Mixed-Use 3.5 FAR

The subject site is located directly across King George Blvd from Tien Sher’s anticipated ‘Whalley District’ development, set to replace the recently closed-down Flamingo Hotel and Bar. Combined, both projects would mark the beginning of renewal and transformation of the area surrounding King George & 108 Avenue, which has become notoriously run-down over the past few decades. This area is designated as a ‘Historic District’ in the City Centre Plan, due to its historical significance as the place of Surrey’s early urban beginnings surrounding the former ‘Whalley’s Corner’ Gas Stop.

For more on the application:

https://apps.surrey.ca/Online-Development-Inquiry/?year=19&seq=0048

A development application has been submitted for a new mixed-use project on 104 Ave near Whalley Blvd. The subject site is made up of 3 existing properties that span the block between 104 Ave and Central Ave just east of Whalley Blvd. The site is currently occupied by a run-down early 1970’s strip mall known as ‘Plaza 104’.

According to details of the development application, the applicant – Andrew Cheung Architects – is seeking to rezone the property and amend both the Official Community Plan and City Centre Plan for increased density from 3.5 FAR to 5.5 FAR to allow for a phased 1149 unit mixed-use development containing 10,720 sq.ft. of commercial space. This translates into approximately 3 high-rise residential towers above retail. In addition, the development would dedicate a new north-south road through the site, as well as 2 new lanes as per the City Centre Plan.

The current application is seeking a Development Permit for phase 1, which is to contain a single tower (383 units) and all 10,720 sq.ft. of commercial space on a newly subdivided parcel fronting 104 Avenue. The remaining phases of the project to the south would be subject to future applications.

Site in context of the City Centre Plan showing future road and lane dedications Subject Site on 104 Avenue east of Whalley Blvd containing a 1970’s strip mall Birds-eye view of site looking south from 104 Ave

For more on the application: https://apps.surrey.ca/Online-Development-Inquiry/?year=19&seq=0060

After nearly 2 years of construction, the Surrey Central Station north station house expansion officially opened to the public this weekend. Designed by OMB Architects, the new 2-storey station house is now the largest entrance at the station, fronting directly onto the corner of Central Avenue and City Parkway across from Civic Plaza.

The new station house features a contemporary, open, and airy design consisting of glass, concrete, and wood materials, as well as a prominent new First Nations art installation suspended from the ceiling – ‘The Sea Captain’ by Marianne Nicolson. A new retail unit has also been added to the station next to the entrance fronting Central Avenue, but has yet to be occupied by a tenant.

New entrance fronting Central Ave Corner of Central Ave & City Parkway Looking west down Central Avenue New entrance on City Parkway New entrance with bike racks and benches on City Parkway New ticket and fare gate concourse Fare gate concourse and art installation

Escalator to second floor concourse

2nd floor concourse Wayfinding signage on second floor concourse

Connection to south station entrance New platform level stairs, escalator and elevator

This latest upgrade to Surrey Central Station is just the beginning of an even larger expansion and re-configuration to come in the future. The lands immediately west of the station, where the current North Surrey Recreation Centre and Bus Loop sit – known as the ‘Centre Block’ are expected to be redeveloped in the coming decade. With that will come the removal of the suburban-style bus loop and re-positioning of bus bays onto streets surrounding the station. A major overhaul of the station is expected at that time to modernize and better integrate it into its evolving urban context.

December 2018 – UrbanSurrey

Blackwood Partners has submitted a development application for the much anticipated Central City 2 office tower – proposed for the corner of King George Blvd and Old Yale Road on the site of a former Best Buy. The 25-storey tower designed by ZGF Architects is to be built to Class AAA and LEED Platinum standards and contain over 500,000 SF of office space, and 20,000 SF of ground level retail.

The proposed design of the tower has undergone considerable revision since first announced back in November 2017. The tower now features copper / reddish toned shading fins on its exterior, and a refined, more cohesive massing and podium. The tower also features expansive green roof decks, premium fitness facilities for office tenants, bike lockers, electric vehicle charging, high-speed elevators, and a ground level urban plaza, anchored by a restaurant, café, and retail.

New plaza at corner of Old Yale Road & City Parkway Conceptual ground level floor plan Office tower views Premium fitness facilities for office tower tenants

Following the completion of the original Central City office tower and SFU campus back in 2003, Central City 2 will form the next phase of a long-term vision to redevelop the remainder of the Central City Shopping Centre site. While just conceptual at this point, the long-term plan would see the remaining parking lots to the north redeveloped with mixed-use development and new streets. The mall itself is envisioned to be reconfigured to include a number of new tower sites, and a large new plaza entrance fronting Holland Park on Old Yale Road – mirroring the existing Central City Plaza to the north and creating a connection through the mall linking the city’s civic core to Holland Park.

Along with the recently submitted development application, Blackwood Partners has also now begun marketing the tower for lease, and will be opening a presentation centre in the Central City Shopping Centre in early 2019. The current leasing brochure can be found here.

A proposal to revitalize an existing rental tower and create 63 new rental units at King George Blvd & 98th Avenue was stalled by Surrey’s new Council on Monday, after being denied 1st & 2nd readings for not looking satisfactory enough, in Council’s opinion. The application, which is proposing to convert an existing 3-storey commercial building on site to rental residential, and upgrade the exterior of the 18-storey tower behind it, was sent back to staff to work with the applicant on unspecified revisions.

Designed in partnership with MCM Architects and PWL Landscape Architects, the project would bring a welcome facelift to the existing buildings on site, originally completed in 1982, as well as improve the surrounding streetscape. Aside from aesthetic upgrades, the primary objective of the project is to create 63 new rental units on site through the conversion of the existing 3-storey commercial building along King George Blvd. Details of the proposed upgrades include:

  • Modernization and conversion of the existing low-rise commercial building to rental residential. Exterior cladding to be replaced with new materials consisting of high quality white fibre cement panels, and charcoal seam metal cladding.
  • Landscaping along King George Blvd enhanced and modified to suit residential use and layout
  • New plaza at the north-east corner of the site to help activate the streetscape along King George Blvd
  • The existing 18-storey tower to receive new exterior paint and glass balcony rail replacements with colour enhancements.

Proposed exterior upgrades and residential conversion along King George Blvd Elevation of proposal looking north along King George Blvd

Despite the high quality materials proposed, and thoughtfully designed plan which works within the given site constraints, Council was of the opinion that the design was not suitable enough to be allowed to proceed. Without giving any specific recommendations on how to improve the design, the project was sent back to staff to work with the applicant on revisions to the plan, despite staff already working closely with the design team to date. The building’s modernization, and the delivery of new rental units to City Centre is now delayed pending unclear revisions, until the project can return to Council for consideration once again.

The conversion is supported by Surrey Staff as the existing commercial building has long suffered from poor vacancy rates and high tenant turn-over due to physical attributes of the building, and its poor integration with the neighbourhood. The proposed residential use is seen as appropriate for this location, being across from a SkyTrain station and the developing context of the area.

Proposed site plan including public realm and streetscape enhancements

The Surrey Village Tower currently contains 227 rental units in the existing 18-storey tower, managed by RealStar. The addition of the proposed 63 new units would bring the total rental units to 290.

February 2018 – UrbanSurrey

The City of Surrey has been invited to participate at this year’s Les Marché International des Professionels de l’immoblier (MIPIM) – taking place March 13-16 in Cannes, France. Surrey is the only Western Canadian city participating at the conference – but will be joined by Montreal, Toronto, Hamilton, and the Niagara Region who will also have a presence.

MIPIM is one of the largest and most prestigious real estate conferences in the world. It has been the international stage where Toronto’s Waterfront Project and Montreal’s Downtown Arts & Entertainment District have been profiled and attracted investment. It is also where Bing Thom Architects’ won a Special Jury Award in 2004 for the Central City building – as the world’s best overall new development for its architecture and building innovation.

At this year’s MIPIM, Mayor Linda Hepner has been personally invited to speak on behalf of Surrey in a panel discussion on the topic of City as a Service, the New Urban Reality, as well as participate at a number of related events at the conference. Being invited to participate at MIPIM is an indication of Surrey’s emerging recognition as an internationally relevant city for future growth and investment.

With more than 24,000 real estate investors from over 100 countries in attendance, MIPIM provides a unique platform for promoting Surrey globally as a place to invest, which can help to accelerate the city’s transformation. In addition to Mayor Hepner’s participation at the event, Invest Surrey & Partners will be showcasing Surrey as North America’s ‘Next Metropolitan Centre’ through a presentation centre to be located in the exhibition area of the main venue. Blackwood Partners, the owners of Central City, will also be attending to promote and attract investment in their upcoming ‘Central City 2’ office tower project.

Invest Surrey & Partner’s presentation centre at MIPIM 2018

For more on Surrey’s invitation to MIPIM:

http://www.surrey.ca/bylawsandcouncillibrary/CR_2018-R023.pdf

WestStone Group’s Evolve in West Village has been progressing at a swift pace lately – having now reached a height of 28 storeys. With 7 more levels to go + a 2-storey rooftop amenity before reaching its final height of 37 storeys – the building should be topped out around mid-april. It can be expected to take another 6-8 months following that to reach full completion – putting an occupancy date somewhere near the end of 2018 / early 2019.

Evolve is Phase 4 of WestStone’s 8-phase, master-planned West Village neighbourhood. It will consist of 389 condo units, 13 townhouse units, and a 3-storey commercial building containing ground-level retail with office above.

Looking north on 133 St Looking east from 133 St Looking east through a future pedestrian corridor towards Civic Plaza Looking south on 133 St Looking east along Central Avenue Townhouse units along Central Avenue North facade of tower 3-Storey retail/office component on Central Avenue Looking south from parkette at Wave Looking south – Wave parkette and public art sculpture in foreground South side of office/retail building

For more on Evolve:

https://www.surrey.ca/bylawsandcouncillibrary/PLR_7912-0325-00.pdf

The long awaited opening of Civic Hotel may finally be just around the corner. After numerous delays – having originally been set to open back in November – the hotel is finally showing signs that it is nearing completion. This week, fencing came down from in front of the building’s main lobby and Dominion Bar + Kitchen fronting Civic Plaza. In addition, landscaping has been planted next to Dominion’s patio, and a newly opened portion of Central Avenue. Signage for Dominion has also been installed on the awning.

While no official date has been set for opening, according to the Dominion Bar + Kitchen website, the restaurant is tentatively scheduled to host its first event – a comedy show – on April 21, 2018. The Marriott reservations website is now taking bookings for Civic Hotel for dates beginning on March 28, 2018 (although the available booking date has been pushed back in the past).

Despite looking nearing completion, it seems we will still have to wait another month or two before the hotel and restaurant open. Numerous things remain to be finished on the building including a number of additional signs to be installed, the removal of a construction elevator on the condo portion of the building, the completion of Civic Plaza lane on the north side of the building, the construction of Prado Cafe on the north side, and the finishing of numerous retail units along City Parkway. It is clear now that the building will open in phases – with the Hotel and Dominion Bar + Kitchen opening first, retail units along City Parkway likely following later this spring, the Condo tower by summer, and the 5-storey KPU campus this fall.

According to sources working on the project – one reason for the delayed opening of the building has been a water leak, affecting the elevator shaft of the main tower. This has delayed the removal of the exterior construction elevator for several months, as well as the exterior finishing of the north side of the tower, where the future Prado Cafe, and an exterior green wall will be. Rumours on the forum SkyscraperPage this week indicated that the construction elevator may finally be coming down by next week, which would hopefully help wrap up the exterior of the building prior to the hotel’s opening in less than 2 months. Regardless, it seems the building will remain an active construction site (at least on the inside) on the main tower and KPU portion, while the hotel and restaurant open on the other.

Dominion Bar + Kitchen nearing completion fronting Civic Plaza Landscaping along Central Avenue next to the Dominion Bar + Kitchen Patio Staircase and entry to Dominion Bar + Kitchen Patio New sidewalk along Central Avenue next to Dominion Bar + Kitchen Patio Dominion Bar + Kitchen + Civic Hotel Entrance along Civic Plaza Lane Daytime shot of Dominion Bar + Kitchen – additional signage for Civic Hotel still to be installed on podium Dominion Bar + Kitchen featuring numerous doors/windows which will open to the Plaza Civic Hotel Lobby Civic Hotel Lobby Civic Plaza Lane in front of Hotel Lobby

104 Avenue – UrbanSurrey

View looking west along 104 Avenue from King George Blvd

Surrey Council gave 1st & 2nd Readings on Monday night to Bosa BlueSky’s next project in Surrey City Centre – Brightside – which will now head to Public Hearing and 3rd Reading (Preliminary Approval) in 2 weeks. The project, which has been under application for the past 2 years, is set to transform the former Brick / Sears Outlet store site at City Parkway & 104 Avenue, which has been sitting vacant for numerous years now. Overall, the application is seeking:

  • A General Development Permit (Form & Character) for the entire site to allow for a phased, mixed-used development consisting of 3 high-rise and 2 low-rise buildings, including:
    • 40-Storey residential tower with ground floor retail (Phase 1)
    • 50-Storey mixed-use residential tower with ground floor retail and 17 floors of office in a stepped podium (Future Phase)
    • 50-Storey residential tower with market and rental units (Future Phase)
    • 2.5-Storey market-hall commercial building
    • 2-Storey amenity building
  • A Detailed Development Permit for phase 1 of the project.
  • OCP Amendment and City Centre Plan amendments to allow for up to 7.5 FAR (9.2 FAR net) density.
  • Rezoning
  • Consolidation from 2 existing lots to 2 new lots.

View looking north along City Parkway from Surrey Central Station View from public and amenity space within interior of site looking south View looking east along 104 Avenue Future ‘Market-hall’ commercial building in centre of site as part of future phases.

Designed by Perkins & Will, the first phase of the project, a 40-Storey residential tower with ground-floor retail, is to be located at the corner of City Parkway and 104 Avenue and will include:

  • 418 Market Residential Units
  • 2,831 sq.ft. of ground floor Retail

The remaining buildings, subject to future Detailed Development Permit applications, will be located further east along 104 Avenue and north along 105 Avenue. The tallest of the towers, the 50-Storey mixed-use building with 17-Storey office podium, would become the new tallest in Surrey once complete, assuming no other building surpasses it by then, at 554 ft. (169m). The two future low-rise amenity, and market-hall buildings located in the centre of the site are to be set within a publicly accessible plaza that will invite people into the site from 104 Avenue. The plaza will be activated by retail and restaurant spaces at grade, as well as landscaping, and public art, subject to future detailed design.

In total once all phases are complete, the project will include:

  • 1,352 Residential Units (including 200 rental units)
  • 202,146 sq.ft. of Office
  • 37,049 sq.ft. of Retail

In addition to the buildings on site, the project will also bring into alignment the intersection of City Parkway and 104 Avenue. The north and south portions of City Parkway on either side of 104 Avenue currently do not connect. This alignment is expected to be completed as part of the first phase, with tower 1 to be aligned on an angle with the newly constructed City Parkway.

Phase 1 of the project is expected to be completed by 2025, with the remaining buildings to follow later in the decade. For more on the project:

https://www.surrey.ca/bylawsandcouncillibrary/PLR_7918-0350-00.pdf

Public consultation is set to get underway this month for the proposed Surrey Langley SkyTrain (SLS) extension, as well as the future of rapid transit along 104 Avenue & King George Blvd.

In 2014, the regional Mayors Council identified Fraser Highway, King George Boulevard, and 104 Avenue as priority corridors for rapid transit South of the Fraser in the 10-Year Vision. Following a study looking at combinations of SkyTrain, LRT, and Bus Rapid Transit for the corridors, the Mayors Council decided on 27-km of urban-style LRT on dedicated track (separate from traffic) on each of the corridors to be built over 2 phases:

  • Phase 1: Surrey-Newton-Guildford Line on 104 Avenue & King George Boulevard
  • Phase 2: Surrey-Langley Line on Fraser Highway

With funding in place to cover the entire first phase, and construction set to begin this year – a last minute request was made in 2018 by Surrey’s new Council to the regional Mayors’ Council to suspend the Phase 1 Surrey-Newton-Guildford LRT line and re-direct funding to the Phase 2 Surrey-Langley line instead, while switching the technology of the Phase 2 line to SkyTrain. The Mayors’ Council voted to move forward with this request, and directed TransLink to begin planning work for SkyTrain on Fraser Highway while at the same time re-visit rapid transit plans for 104 Avenue and King George Boulevard corridors.

Proposed Surrey Langley SkyTrain route and conceptual stations

The switch of priorities to the Phase 2 Fraser Highway line and changing its technology to SkyTrain has had implications both in budget and timeline. The funding that was allocated for the full Phase 1 Surrey-Newton-Guildford LRT line has been identified as inadequate to fund the entire Fraser Highway SkyTrain extension to Langley. Pending a future round of funding (timeline unclear), the line may have to be phased, with the current funding getting the line potentially only as far as Fleetwood. Start of construction and delivery of new rapid transit South of the Fraser is also now delayed by approximately 2 years as a result of the switch.

Despite the funding and timeline uncertainties, planning work is nonetheless well underway for the new SLS line, which will need to involve a significant re-evaluation of land-use plans along the Fraser Highway corridor to support SkyTrain, completion of a number of supportive studies, and extensive Public Consultation. In a project update report to Surrey Council this week – a preliminary timeline was given for this work by TransLink, with start of service targeted for 2025.

To run concurrently with the SLS planning and consultation work will be a planning process to ‘refresh’ the South Fraser Rapid Transit Strategy for delivering the Mayors’ Council fully envisioned 27km of Rapid Transit along each of the Fraser Hwy, King George Blvd, and 104 Ave corridors. This refresh will look to re-examine and engage the public on what rapid transit along the remaining corridors could look like, now that SkyTrain has been chosen as the technology for Fraser Hwy. The 2013 Rapid Transit Alternatives Study identified Bus Rapid Transit (BRT) for these corridors based on a scenario with SkyTrain on Fraser Hwy. With much LRT planning work having now been completed however, for the 104 Ave and King George Blvd corridors, it’s possible that LRT could still be an option for them rather than BRT, especially given Surrey’s long-term rapid transit vision for an extensive LRT network on major arterials across the City.

The first round of Public Consultation on the SLS line and South Fraser Rapid Transit refresh gets underway on April 11 in Langley, with open houses in Surrey on April 15, 16, and 17. TransLink has also recently launched an online survey where you can voice your feedback on the proposed SLS line. Open House times are set for the following dates and locations between 3-8pm:

  • Thursday, April 11 – Langley City Hall
  • Monday, April 15 – Surrey Sport & Leisure Complex (Fleetwood)
  • Tuesday, April 16 – Surrey City Hall
  • Wednesday, April 17 – Newton Seniors Centre

More info on the land-use planning review process for the Fraser Highway Corridor being undertaken by the City of Surrey can be found here: https://www.surrey.ca/bylawsandcouncillibrary/CR_2019-R059.pdf

A development application has been submitted for a new mixed-use project on 104 Ave near Whalley Blvd. The subject site is made up of 3 existing properties that span the block between 104 Ave and Central Ave just east of Whalley Blvd. The site is currently occupied by a run-down early 1970’s strip mall known as ‘Plaza 104’.

According to details of the development application, the applicant – Andrew Cheung Architects – is seeking to rezone the property and amend both the Official Community Plan and City Centre Plan for increased density from 3.5 FAR to 5.5 FAR to allow for a phased 1149 unit mixed-use development containing 10,720 sq.ft. of commercial space. This translates into approximately 3 high-rise residential towers above retail. In addition, the development would dedicate a new north-south road through the site, as well as 2 new lanes as per the City Centre Plan.

The current application is seeking a Development Permit for phase 1, which is to contain a single tower (383 units) and all 10,720 sq.ft. of commercial space on a newly subdivided parcel fronting 104 Avenue. The remaining phases of the project to the south would be subject to future applications.

Site in context of the City Centre Plan showing future road and lane dedications Subject Site on 104 Avenue east of Whalley Blvd containing a 1970’s strip mall Birds-eye view of site looking south from 104 Ave

For more on the application: https://apps.surrey.ca/Online-Development-Inquiry/?year=19&seq=0060

With Doug McCallum’s win in last weekend’s election, Surrey appears to be in for change. Campaigning heavily on LRT and Safety, the topic of discussion now is whether he will deliver on his promise to ‘scrap’ LRT and ‘replace’ it with SkyTrain. It appears the majority of Surrey residents are in favour of this – fuelled by non-stop negative publicity of LRT in the media – but what does an LRT to SkyTrain ‘switch’ actually mean for Surrey? A few key implications to consider:

SkyTrain vs LRT – 2 different routes

A misconception that many who ‘voted’ for SkyTrain over LRT may have may have is that the proposed LRT will simply be ‘switched’ to SkyTrain. This is not the case – each would run along a different route. Let’s look at the difference:

LRT – City Centre-Newton-Guildford: The proposed ‘Phase 1’ LRT route – with secured funding and significant planning and design work already completed – is planned run from Guildford along 104 Avenue to City Centre, then south on King George Blvd to Newton. This is known as the ‘L’ Line or Surrey-Netwon-Guildford Line – serving Surrey’s most populated, and urban town centres.

Phase 1 LRT route along 104 Ave & King George Blvd + future Phase 2 route to Langley

SkyTrain – Fraser Highway: Doug McCallum’s SkyTrain – which would need to be planned and designed from scratch – would provide no rapid transit to Guildford or Newton (Surrey’s most populated / urban town centres) – but instead be an extension of the existing Expo Line down Fraser Highway to Fleetwood, Cloverdale (Surrey’s least populated / urban town centres) and Langley.

SkyTrain extension to Langley along Fraser Hwy through low density suburbs / ALR to Langley

The Land-Use Difference

LRT: The proposed ‘Phase 1’ LRT route would serve Surrey’s most established urban corridors with the highest densities – 104 Avenue and King George Blvd. Guildford Town Centre contains the regions 2nd largest shopping centre, numerous high-rises and offices. Further, the currently underway Guildford-104 Avenue Corridor Plan which is set to become adopted in 2019, has designated land all along 104 Avenue between City Centre and Guildford for increased urban densities appropriate for a rapid transit corridor. A similar plan is set to follow for the King George corridor between City Centre and Newton. Simply put – 104 Avenue and King George Blvd are the most appropriate corridors for initial rapid transit expansion in Surrey due to their already underway land-use planning for higher density, and their existing densities, land-use, and most urban character of Surrey’s corridors.

Phase 1 LRT route along existing urban corridors with planned density Guildford – 104 Avenue Corridor Plan – urban density planned along LRT route

SkyTrain: Doug McCallum’s SkyTrain would run down Fraser Highway which currently has no land-use plans for significant urban density underway, and is currently of the lowest density and suburban of corridors in Surrey. The SkyTrain route would run through:

  • Green Timbers Forest for the first 2km of its route
  • the low density suburban neighbourhood of Fleetwood for the next 5km
  • ALR farm land for the next 2km
  • and finally low density suburban Clayton/Cloverdale and Langley for the remaining 6km of the route

This route would have the lowest densities of any SkyTrain corridor in the region – including significant stretches through forest and ALR farm land – unseen anywhere else on the SkyTrain system. SkyTrain along Fraser Highway would require significant land-use changes along Fraser Highway to justify it – including significant increases in density, high-rise towers, and transit-oriented development – similar to elsewhere along the SkyTrain network. This would require changes to the Official Community Plan (OCP) – ironically Doug McCallum campaigned against OCP amendments.

Simply put – this type of development is incompatible with the scale and character of the Fraser Highway corridor that is predominantly newer single family homes and townhomes. Many living along that corridor would surely object to such drastic land-use changes appropriate for a SkyTrain line.

SkyTrain extension through low density suburbs / ALR with no planned urban density

From a land-use planning perspective – it makes the most sense to serve the highest density corridors and urban centres (104 Avenue – King George Blvd) with rapid transit prior to lower density corridors such as Fraser Highway. Instead, a SkyTrain extension over LRT would do the exact opposite of what makes sense. While it is important to provide a rapid transit link to Langley, and connect the communities of Fleetwood, Clayton/Cloverdale with regional rapid transit – from a land-use and planning perspective these areas are lower priority than Guildford and Newton – and Fraser Highway does not have density appropriate for SkyTrain. In an ideal world, Langley would be serviced by long-distance commuter rail such as all-day WestCoast Express – but realistically – LRT may be the best option for serving Langley down Fraser Highway as a Phase 2 project – given the density, scale, and character of that corridor.

Uncertain Timeline

LRT: Funding for the proposed ‘Phase 1’ LRT route is “in the mail” from the Federal and Provincial Governments. Significant planning, consultation work, and design has been underway for years, and the project is now at the procurement stage with construction set to begin in 2019 and completion by 2024.

LRT scheduled to begin construction in 2019 – years of planning, consultation, design already complete.

SkyTrain: Doug McCallum claims that secured funding for LRT can simply be ‘switched’ to fund a SkyTrain extension to Langley instead of the Guildford Newton line. While this may be possible, as the funding doesn’t specify a type of rail – the fact is – no planning, consultation, or design work has been completed on a SkyTrain extension down Fraser Highway. The amount of time and additional resources that would need to go into a SkyTrain extension prior to its construction would not only delay the project for an unforeseen number of extra years – pushing completion of this line to the late 2020’s.

By that time, Phase 2 of the LRT is likely to be under construction – resulting in Surrey having 2 new rapid transit lines by the late 2020’s instead of just a single SkyTrain extension down low-density Fraser Hwy within the same time frame.

While these reasons aren’t exhaustive in the debate – they are very key ones that have been surprisingly absent talking points. Surrey residents may not have been the best informed on the SkyTrain vs LRT debate thanks to the media – to make an educated decision that weighs more factors than just ‘speed of service’ and ‘glamour of SkyTrain vs LRT’ – but in the end it may not matter. The LRT project is likely too far along at this stage and with too much else to consider to simply be ‘switched’. It is being led by non-partisan land-use and transit planning experts in the Planning & Transportation Departments (not the former Mayor or Councillors as some may believe) – experts who should be leading such projects – rather than transit planning on a whim by politicians and voters.

The City of Surrey began a series of 3 open houses on Thursday for Phase 1 of the upcoming Surrey LRT project. This latest public engagement is the 3rd round of open houses on Phase 1 the project, providing refined plans based on public input from previous consultations. Presented at the open house were preliminary station designs, road designs, information on construction planning, environmental and socio-economic study results, and more. A full set of the Open House Boards can be found here.

Station Designs

Overall, stations are designed to be highly visible, well-lit, and well integrated into the community – accessible by well-marked pedestrian crossings providing universal accessibility for all riders. Lengthy platform shelters protect riders from weather, and include space for ATM’s, information boards, seating, and more – while maintaining a clear line of sight to the street and approaching trains. Stations will in most cases be located in the centre median of the street, with the exception of King George, Surrey Central and Newton Town Centre – where they will be plaza oriented, or off to the side. Public art will also be integrated into stations along the route.

Roadway Design

LRT will run on its own dedicated track for the entirety of the line, with the exception of City Parkway where it will be integrated into a pedestrian plaza. Placement of the LRT track will vary – typically located in the centre median for most of the route, but off to the side in some sections.

Roadway design for 104 Avenue will consist of LRT in the centre median, and 1 traffic lane in each direction, widening to include an additional turning lane at major intersections. The 104 Avenue design will also provide upgraded and enhanced sidewalks, pedestrian crossings, and connections to stations. Currently 104 Avenue functions as a non-pedestrian friendly, busy arterial for cars. A re-purposed 104 Avenue with LRT will transform the street into a calmed, pedestrianized and transit-oriented corridor, supported by multi-family housing and streetfront shops along the route. The newly widened 100 Avenue and existing 108th Avenue corridors will become the new car-prioritized east-west routes between City Centre and Guildford while 104 Avenue will be the pedestrian/transit prioritized corridor.

Roadway design for King George Blvd will retain 2 traffic lanes in each direction while allowing for LRT in the median for the majority of the route. Sections of King George in City Centre will see LRT routed off to one side. New separated bike lanes, enhanced sidewalks, and pedestrian crossings will also be a key component of the re-designed King George.

Pedestrianized Plazas at Surrey Central & King George Stations

Taking inspiration from leading cities around the world, Surrey Central and King George Stations in City Centre are designed to be integrated into new pedestrianized public plazas. These plazas will help to create vibrant transfer points between LRT and SkyTrain’s expo line, similar to plaza’s found throughout Europe with multi-modal rail connections running through them. 

Socio-Economic Study: Improved Travel Times

A key finding of the socio-economic study released at the open house, was the improvement in travel times that LRT will offer over the existing 96 B-Line bus service, as well as private automobile. Under Section 7.2 of the study it was found that the existing 96 B-Line service between Guilford-Newton currently takes 29 minutes under ideal conditions. During periods of congestion however, this trip can take longer than 50 minutes. Further, this travel time is expected to worsen as population grows. LRT is able to cut this travel time by up to half, taking a consistent 27-minutes every time, on opening day, and a decade later, due to its dedicated track. In addition to this, LRT offers faster service and improved experience due to:

  • More doors for boarding, significantly reducing stop times at stations, and travel times overall.
  • Nearly twice as frequent peak service as the existing 96 B-Line peak bus service.
  • A smoother, more comfortable ride than B-Line bus, with less stop and go.

96 B-Line subject to traffic congestion – travel times between Guildford and Newton up to 50 mins during peak hours.

Integration with the Community

One of the key benefits of LRT is its integration with the community and streetscape compared to SkyTrain. While SkyTrain serves well as a long distance commuter rail service, LRT is better suited to more localized routes in the region – similar to other cities where there are various tiers of rail transit making up the regional transit network.  Not every line in a city needs to be the same type of rail transit – LRT, Subway, and Commuter Rail are often combined to compliment each other and serve different needs. The introduction of LRT to Metro Vancouver represents a maturing of our rail transit network into a multi-modal system, and it is very likely we will see LRT implemented elsewhere in the region following Surrey.

In Surrey, the 104 Avenue and King George Highway corridors that make up the ‘L’ line are much better suited to urban-style LRT than SkyTrain. Not only is this route more localized than regionally serving, but SkyTrain just doesn’t make sense from a cost perspective, and the impacts that such guideways would have on the streetscapes. Looking at a comparison between SkyTrain guideways in Richmond City Centre and Coquitlam City Centre, it is clear to see how much better LRT integrates with the streetscape and community it passes through, rather than bisecting it with an obtrusive, shadowing, and noisy concrete structure. LRT can transform a streetscape into an inviting, pedestrian friendly, vibrant urban environment – whereas SkyTrain does the opposite. 

Impact of SkyTrain guideways on the urban environment/streetscape vs urban-style LRT

For more on Surrey LRT:

https://surreylightrail.ca

The City of Surrey held a public open house last week on the in-progress, Guildford Town Centre – 104 Avenue Plan. The plan, which has been under study since last year, is seeking to define a vision and prepare a long-range land-use plan to guide future growth along the 104 Avenue Corridor and Guildford Town Centre areas.

Presented to the public at the open house last week were 2 land-use concept options, along with a proposed street network, bicycle and pedestrian network, and parks and open space concept.

Land-Use Concept Option 1: Focused Growth

Land-Use Concept Option 1 seeks to focus growth and density in key areas of the plan, such as along 104 Avenue and areas surrounding Guildford Town Centre. The plan envisions:

  • A continuous stretch of 6-storey mixed-use/apartments (Dark orange) along 104 Avenue
  • Mid to high-rise mixed-use (pink) at 104 Ave & 144 St.
  • Mid to high-rise along 104 Ave east of 148 St and to the north and east of Guildford Town Centre – with the tallest tower heights (purple) concentrated on the former Sears site.
  • 4-storey apartment areas (light orange) dispersed throughout the plan area
  • Townhouses (yellow) in a few areas
  • Single Family housing preserved in a number of areas, mostly west of 148 St.

Land-Use Concept Option 1: Focused Growth

Land-Use Concept Option 2: Dispersed Growth

Land-Use Concept Option 2, while very similar, seeks to disperse growth and densities over the plan area, with lower intensities of density, but increased density covering more area. This includes:

  • A wider continuous stretch of 6-storey mixed-use/apartments (Dark orange) along 104 Avenue
  • Mid to high-rise mixed-use (Pink) to the north and east of Guildford Town Centre.
  • 4-storey apartment areas (light orange) more widely dispersed throughout the plan area
  • Townhouses (yellow) more widely dispersed across the plan area
  • Slightly less preserved Single Family housing.

Land-Use Concept Option 2: Dispersed Growth

Proposed Street Network

The proposed street network adds a number of new local and collector streets to improve connectivity through a finer-grained network. One of these new collectors is the currently underway 105A Avenue connector project which will provide an alternate east-west route to 104 Avenue linking City Centre to Guildford. A long-range new street network is shown on the site of Guildford Town Shopping Centre – envisioning the future redevelopment of this mall into an urban district far into the future – similar to the vision for the Metropolis at Metrotown Shopping Centre site in Burnaby under the Metrotown Plan.

Proposed Bike and Pedestrian Network

The proposed bike and pedestrian network creates a number of new multi-use paths and road-separated bike lanes improving connectivity throughout the plan area. Pedestrian and cycling crossings at busy intersections would be enhanced under the plan to improve safety and streetscape integration. Existing bike lanes would be upgraded to be physically separated from the road.

Proposed Parks and Open Space

The proposed parks and open space plan illustrates how parks, habitat areas, and the city’s Green Infrastructure Network will be integrated into the plan area. A key feature of the plan is a ‘Green Loop’ pedestrian and cycling network stretching east-west with north-south connections – improving non-automobile connectivity in the area and connecting the many parks. In addition to existing parks shown in light green, many new parks are shown in dark green, including expansions to Hawthorne Park.

Future Light Rail Transit (LRT)

An integral part of the 104 Avenue – Guildford Town Centre Plan area will be the new LRT line linking City Centre to Guildford along 104 Avenue, and further south to Newton. This urban-style, low floor, LRT system will not just be a rapid transit line passing through the area, but a fully streetscape-integrated, centrepiece of the 104 Avenue corridor. Combined with a continuous 6-storey mixed-use density along 104 Avenue, the corridor will be transformed into a transit/pedestrian-oriented and prioritized streetscape, similar to precedents in Europe and elsewhere around the world. The LRT will support the densities along the the 104 Avenue Corridor, and integrate seamlessly into the community – unlike SkyTrain which bisects and has a negative visual and physical impact on the streetscape.

To find out more about the Guildford Town Centre – 104 Avenue Plan, and participate in the public survey – visit:
http://www.surrey.ca/city-services/24723.aspx

Whalley Blvd – UrbanSurrey

Vancouver developer Rize is set to bring their latest and most ambitious project to date before Surrey Council on Monday for 1st & 2nd Readings, and approval to proceed to Public Hearing. Passages as it’s called, is a proposed master-planned mixed-use development at 10138 Whalley Blvd consisting of market condos, market rental apartments, retail, and daycare space, all situated within a European-style ‘piazza’ public plaza. In total the project is proposing:

  • 3 High-Rise towers and 1 Low-Rise (6, 23, 32 & 39 Storeys) containing 954 Market Condo Residential Units
  • 2 Mid-Rise towers (13 Storeys each) containing 172 Market Rental Residential Units
  • 18,116 sq.ft. of Ground Level Retail Space
  • 4,252 sq.ft. of Daycare Space
  • A 69,602 sq.ft. Publicly Accessible ‘Piazza’-Style Public Plaza

Rendering of central public ‘Piazza’ space within Passages development

Designed by London, UK based Alison Brooks Architects, Passages brings a fresh departure from the standard point tower above podium form, commonly found throughout Metro Vancouver. Instead, the project consists of 6 irregularly-shaped buildings of varying heights, clustered around a ‘Piazza’-style public plaza.

The design takes inspiration from coastal BC forests, incorporating references to ‘textured tree bark’ on building facades, and the use of earth tones and materials. Interspersed single and double-storey units are present throughout the towers, adding variation in form and glazing pattern. The 6-storey building is a modern interpretation of the traditional ‘British mansion block’ merged with ground floor townhouses.

The site’s perimeter and courtyard are structured as open, barrier-free spaces that the public and residents can share and enjoy. A series of four distinct piazzas, City Piazza, Park Piazza, Central Piazza and Neighbourhood Piazza, are linked by narrow urban groves between buildings and enriched streetscape edges.

The Landscape Architect on the project is Vancouver’s PWL Partnership tasked with designing the publicly accessibly open spaces comprised of the four landscaped piazzas. These spaces are animated with community agricultural gardens, an urban square with seating, a children’s play area, a great lawn for event and performance space, a yoga and exercise zone, a community harvest table, and an outdoor barbeque and games table space to encourage the public and residents to interact and socialize.

Passages will replace two existing and aging, wood-frame, 4-storey apartment buildings known as Fraserview Court, built in the 1970’s. Rize is proposing to offset the loss of the 154 existing rental residential units on site by providing 172 new rental residential units in two new 13-Storey concrete mid-rises as part of re-development. These rental units will be secured for a period of 20-years, through a Housing Agreement with the City. Rize is also assisting existing residents facing displacement through a City policy directed Tenant Relocation and Assistance Plan.

The project is proposed to be built in 3 phases, which includes:

Phase 1 (Targeted Completion: May 2023)

  • 13-Storey Mid-Rise with Market Rental Residential (88 Units), Ground Floor Cafe, and Daycare
  • 23-Storey High-Rise with Market Condo Residential (212 Units)

Phase 2 (Targeted Completion: June 2024)

  • 6-Storey Low-Rise with Market Condo Residential (66 Units)
  • 32-Storey High-Rise with Market Condo Residential (304 Units), and Ground Level Retail

Phase 3 (Targeted Completion: August 2024)

  • 13-Storey Mid-Rise with Market Rental Residential (84 Units), and Ground Level Retail
  • 39-Storey High-Rise with Market Condo Residential (372 Units)

In terms of approvals, the development is seeking:

  • City Centre Plan amendment to increase density on the site from 3.5 FAR to 5.5 FAR
  • Official Community Plan amendment to increase density on the site from 3.5 FAR to 5.5 FAR
  • Rezoning from Multiple Residential 45 Zone to Comprehensive Development Zone (Based on RM-135 & C-8)
  • Subdivision from 1 to 3 lots
  • Development Permit to allow for 3 High-Rise Buildings, 2 Mid-Rise Buildings, and 1 Low-Rise Building.

For more information on Passages:

https://www.surrey.ca/bylawsandcouncillibrary/PLR_7918-0289-00.pdf

A development application has been submitted for a new mixed-use project on 104 Ave near Whalley Blvd. The subject site is made up of 3 existing properties that span the block between 104 Ave and Central Ave just east of Whalley Blvd. The site is currently occupied by a run-down early 1970’s strip mall known as ‘Plaza 104’.

According to details of the development application, the applicant – Andrew Cheung Architects – is seeking to rezone the property and amend both the Official Community Plan and City Centre Plan for increased density from 3.5 FAR to 5.5 FAR to allow for a phased 1149 unit mixed-use development containing 10,720 sq.ft. of commercial space. This translates into approximately 3 high-rise residential towers above retail. In addition, the development would dedicate a new north-south road through the site, as well as 2 new lanes as per the City Centre Plan.

The current application is seeking a Development Permit for phase 1, which is to contain a single tower (383 units) and all 10,720 sq.ft. of commercial space on a newly subdivided parcel fronting 104 Avenue. The remaining phases of the project to the south would be subject to future applications.

Site in context of the City Centre Plan showing future road and lane dedications Subject Site on 104 Avenue east of Whalley Blvd containing a 1970’s strip mall Birds-eye view of site looking south from 104 Ave

For more on the application: https://apps.surrey.ca/Online-Development-Inquiry/?year=19&seq=0060

Rize Alliance, the developer behind Wave and the recently released Linea, has submitted an application for their next development in City Centre. Located at 10138 Whalley Blvd just south of 102 Avenue, the project would replace an existing 3-storey walk-up apartment complex built in the 1970’s.

While not many details have been released so far, what is known is that the project is to contain 1,070 units – likely within 2-3 towers above a mixed-use podium base. The subject site is currently designated ‘Residential Mid to High Rise 3.5 FAR’ in the City Centre Plan, and is located just to the south of Anthem Properties ‘Georgetown‘ development, which recently received 3rd reading for phase 1 its 7-tower master-planned community.

The new Rize application is currently under initial review at the City of Surrey. More details can be expected once the project proceeds to Council.

Subject Site containing an existing 3-storey apartment complex Subject site containing an existing 3-storey apartment complex Subject site within City Centre Plan Subject site at 10342 136A St

A development application has been submitted for a 35-storey residential tower above a 4-storey podium, as well as a 3-storey stand-alone commercial building on a long vacant, grassed site, on Whalley Blvd just north of Canadian Tire near Central Avenue. The address of the site is actually 10342 136A St, as the site has frontage on both Whalley Blvd and 136A St.

Details of the application indicate that the residential tower and podium are to contain 341 units, with 20,000 sq.ft. of ground floor retail, while the 3-storey stand-alone commercial building is to contain 23,800 sq.ft. of floor area (presumably office). In addition to the proposed buildings, the site has a future green-lane running east-west through it as per the City Centre Plan that will need to be dedicated as part of the development. Presumably, the 3-storey standalone commercial building will be located to the north of the lane, with the 35-storey tower and retail to the south.

The application is being represented by Focus Architecture Inc., who also designed the D’Corize tower at 104 Ave & University Dr, as well as the recent Delta Rise in North Delta. No renderings or further details of the application have been made public at this time. The site is directly to the north of Anthem Properties’ 7-tower ‘Georgetown’ development.

Subject site within the City Centre Plan Birds-eye view of site from Google Maps Subject site from Whalley Blvd looking north-west Subject site from Whalley Blvd looking south-west

For more on the application:

https://apps.surrey.ca/Online-Development-Inquiry/?year=18&seq=0141

City Centre Update – UrbanSurrey

The December Issue of the City Centre Monthly Update is now out at SurreyCityCentre.ca. This month’s newsletter includes a round-up of new Development Applications, Council Approvals, and Construction activity over the past month.

New Development Applications

Four new major development applications were submitted within City Centre during the past month of November 2020, bringing the total number of major projects under initial review to 34. This represents approximately 27 HighRises (

October 2016 – UrbanSurrey

Further to the update earlier this month on the SFU expansion project, more site clearing has taken place adjacent to the project.

As of Oct 27th, trees on 3 lots to the west of the project were cleared, and the site is now being prepped for what appears to be a construction staging site for the SFU project. No development applications have been submitted on the lots, all that is known is that they are owned by the City of Surrey. When complete a new Urban Green Lane will run North-South between these recently cleared lots and the SFU project, as shown on the plan below.

With this added clearing of trees, the area west of University Drive known as West Village continues its transformation into Surrey’s first high-density urban neighbourhood.

Central City Shopping Centre has recently announced plans and begun work on a major renovation of aging parts of its complex. As part of the initial phase, the 2-storey portion of the mall between Wal-Mart and T&T Supermarket is currently being updated with a new contemporary look featuring wood paneling around balcony areas and a wave-like feature in the atrium. It is expected that once this phase is completed, upgrades will be expanded to remaining portions of the mall in need of updates.

At present the mall is a haphazard mix of interiors dating from various eras of expansions and renovations. Some of the oldest portions have not been updated since the 90s when the mall was known as Surrey Place. This latest update should help to bring a cohesive look to the complex, and hopefully attract new tenants. Since opening in the 1960’s the mall has seen much transformation and numerous expansions, the most significant being the addition of SFU and the Office Tower in 2003. It is hoped that this latest renovation will help to attract new tenants to the shopping centre which has seen a resurgence of activity lately, with the mall now busier than it’s been in over a decade thanks to the mix of uses in the complex. The Central City leasing brochure currently shows a large section in the centre of the mall where a corridor used to be as up for lease. It’s anticipated that a future phase of renovations will involve the re-opening of this wing adding new retail space and improved mall connectivity.

Beyond this current wave of renovation there remains the potential for even further evolution of the complex, particularly where surface parking now exists along its King George Blvd frontage, as well as its frontage facing Holland Park along Old Yale Rd. These two sides of the mall hold tremendous opportunity for re-development and transformation of the shopping centre as Surrey City Centre grows, and Central City evolves into Surrey’s key downtown destination shopping centre.

http://www.centralcity.ca

Progress continues on the SFU Surrey ‘Sustainable Energy and Environmental Engineering Building’ at 102 Avenue and University Dr. Over the past few weeks, the site has been cleared and is now undergoing excavation to allow for the construction of a single level of underground parking below what will be a 5-storey building. Despite the activity on site, the project has yet to receive 4th-reading / final approval from the City of Surrey. The project is being fast-tracked to meet a deadline for Federal funding, which stipulates the building must be substantially completed by April 30, 2018. Preliminary Approval was granted in July, and it is expected final approval will come later this year.

More on SFU Surrey expansion:

https://urbansurrey.wordpress.com/2016/07/11/update-sfu-surrey-expansion/

https://www.surrey.ca/bylawsandcouncillibrary/CR_2016-R178.pdf

Further to last month’s Anthem Properties announcement, an application has now been submitted by the developer for a 6-tower mixed-use development on the Save-on Foods / Canadian Tire site at 102 Ave between King George Blvd and Whalley Blvd in Surrey City Centre. This differs slightly from details released on Anthem Properties website indicating a 7-Tower project. Details of the application submitted (Project Number 16-0448) are as follows:

Rezoning from CD to CD (based on RMC-135), development permit for six mixed-used high-rise tower buildings, subdivision from one to six properties.

Rezoning from CD to CD (based on RMC-135) to permit development of a 30-storey mixed use building.

Development permit for a 30-storey mixed-used building.

https://apps.surrey.ca/Online-Development-Inquiry/?year=16&seq=0448

Based on this, it appears Anthem wishes to subdivide the property into 6 parcels for a multi-phased development, starting with a 30-storey mixed-use tower.

While no plans have yet been released, the City Centre road network plan gives an indication of how the site will be parceled, with 2 new roads to run east-west through the large site, and a new urban green lane to run north-south.

More details as they are released.

http://www.surrey.ca/files/CityCentre_Road_Network_Appendix_V.pdf

Dominion Bar + Kitchen and Civic Hotel nearing completion – UrbanSurrey

The long awaited opening of Civic Hotel may finally be just around the corner. After numerous delays – having originally been set to open back in November – the hotel is finally showing signs that it is nearing completion. This week, fencing came down from in front of the building’s main lobby and Dominion Bar + Kitchen fronting Civic Plaza. In addition, landscaping has been planted next to Dominion’s patio, and a newly opened portion of Central Avenue. Signage for Dominion has also been installed on the awning.

While no official date has been set for opening, according to the Dominion Bar + Kitchen website, the restaurant is tentatively scheduled to host its first event – a comedy show – on April 21, 2018. The Marriott reservations website is now taking bookings for Civic Hotel for dates beginning on March 28, 2018 (although the available booking date has been pushed back in the past).

Despite looking nearing completion, it seems we will still have to wait another month or two before the hotel and restaurant open. Numerous things remain to be finished on the building including a number of additional signs to be installed, the removal of a construction elevator on the condo portion of the building, the completion of Civic Plaza lane on the north side of the building, the construction of Prado Cafe on the north side, and the finishing of numerous retail units along City Parkway. It is clear now that the building will open in phases – with the Hotel and Dominion Bar + Kitchen opening first, retail units along City Parkway likely following later this spring, the Condo tower by summer, and the 5-storey KPU campus this fall.

According to sources working on the project – one reason for the delayed opening of the building has been a water leak, affecting the elevator shaft of the main tower. This has delayed the removal of the exterior construction elevator for several months, as well as the exterior finishing of the north side of the tower, where the future Prado Cafe, and an exterior green wall will be. Rumours on the forum SkyscraperPage this week indicated that the construction elevator may finally be coming down by next week, which would hopefully help wrap up the exterior of the building prior to the hotel’s opening in less than 2 months. Regardless, it seems the building will remain an active construction site (at least on the inside) on the main tower and KPU portion, while the hotel and restaurant open on the other.

Dominion Bar + Kitchen nearing completion fronting Civic Plaza Landscaping along Central Avenue next to the Dominion Bar + Kitchen Patio Staircase and entry to Dominion Bar + Kitchen Patio New sidewalk along Central Avenue next to Dominion Bar + Kitchen Patio Dominion Bar + Kitchen + Civic Hotel Entrance along Civic Plaza Lane Daytime shot of Dominion Bar + Kitchen – additional signage for Civic Hotel still to be installed on podium Dominion Bar + Kitchen featuring numerous doors/windows which will open to the Plaza Civic Hotel Lobby Civic Hotel Lobby Civic Plaza Lane in front of Hotel Lobby